Construction · Extra work and change orders

Change order markup calculator.

Enter the cost of the extra work in each category and the markup you apply to it. The page adds them up and shows markup against margin.

Extra work costing $13,400.00 across four categories, with 35% on labor, 15% on materials and equipment and 10% on subcontractors, prices at $16,000.00: a 19.4% overall markup on cost, which is a 16.3% margin on the price.

Sources opened October 26, 2026Runs in your browser

Advertisement

Cost and markup by category

$

Wages, fringes and any labor surcharge you carry.

% on cost

Added on top of the cost above.

$

Purchase price plus delivery.

% on cost

Added on top of the cost above.

$

Rental or owned-equipment rate times hours.

% on cost

Added on top of the cost above.

$

What the subcontractor charges you.

% on cost

Added on top of the cost above.

Your result

Advertisement

One markup does not fit a whole change order

Change order work is rarely one kind of cost. Labor, materials, equipment and subcontracted work carry different risk and different overhead, and the public owner whose method is described below gives each its own percentage. Putting a single blended figure on the total hides which category is paying for your overhead. This calculator keeps the four categories separate and then reports the blended result, so you can see how the mix of costs moves the overall markup.

It also keeps markup and margin apart, because the two get swapped constantly in change order talk. A markup is a percentage of cost; a margin is a percentage of the price. Thirty-five percent on cost is not thirty-five percent of the price, as the worked example shows.

Worked example

Extra work costs $4,200 of labor, $3,000 of materials, $1,200 of equipment and $5,000 of subcontractor work: $13,400.00 in all. With 35% on labor ($1,470), 15% on materials ($450), 15% on equipment ($180) and 10% on subcontractors ($500) the markup is $2,600.00 and the change order price is $16,000.00. Overall that is $2,600.00 ÷ $13,400.00 = 19.4% on cost, and $2,600.00 ÷ $16,000.00 = 16.3% of the price. The percentages in this example are the Caltrans force account rates described below, used as an illustration; your contract sets yours.

How it is calculated

  1. For each category, markup = cost × markup percentage, and category price = cost + markup.
  2. Change order price = total cost + total markup.
  3. Overall markup on cost = total markup ÷ total cost. Overall margin on the price = total markup ÷ change order price, which is always lower than the markup.

The default percentages come from one public owner’s published method. Caltrans’ Local Assistance training Module 8 (January 2026) describes force account payment under CTSS 9-1.04: labor is [(basic hourly wages plus fringe benefits) × labor surcharge percentage + subsistence and travel allowance] × 135%, which is a 35% markup; equipment is rental rate × 115%; materials are (purchase price + delivery) × 115%; and subcontractor force account costs get a 10% markup (× 110%). The same module says the labor surcharge percentage was “currently about 12%”. I did not open the Standard Specifications text itself, so check the edition in your contract. Calculation as of October 26, 2026.

What this does not cover

Sources

Sources

Advertisement

Common mix-ups

  1. Caltrans Local Assistance, Module 8: Payment (January 2026)

Checked against these sources on .

Frequently asked questions

How do I calculate a change order markup?

Add up the cost of the extra work in each category, apply the markup your contract allows to each, and add the markups to the cost. This page does that and reports the overall markup and margin.

What is the difference between markup and margin on a change order?

Markup is a percentage of cost; margin is a percentage of the price. A 35% markup on cost is a 25.9% margin on the price, because 0.35 divided by 1.35 is 0.259.

What markups does Caltrans use for force account work?

Caltrans Local Assistance Module 8 (January 2026) lists labor at 35% on wages plus surcharge, equipment 15%, materials 15% and subcontractors 10% under CTSS 9-1.04. Check the edition in your own contract.

Can I use these percentages on a private job?

Only if your contract says so. They are one public owner’s method and are shown as an example, not as a standard.

Why is my overall markup lower than my labor markup?

Materials, equipment and subcontractor costs carry lower rates, so the blended figure sits between them, weighted by how much of the cost each category is.

Estimate only

This page is a pricing aid, not contract or legal advice. Results use the numbers you enter and the formulas and sources named above, as read on October 26, 2026. Everything runs in your browser; nothing is sent anywhere.